Owner dashboard
Aura Pilot Build 01
37 Aspen Road, Lac Ste. Anne County (Agricultural district)
Preview data — live journey state lands with the Aura Brain service
01
LAND
Complete
02
DESIGN
Complete
03
BUDGET
Complete
04
ESCROW
In progress
05
BUILD
Ahead
Escrow position
Open escrow$301,280
Total milestone value (MID budget, excl. land) — 10 percent statutory holdback on every release
- Funded to escrow
- $30,000
- Released to builder (net)
- $10,800
- Holdback retained
- $1,200
- Awaiting funding
- $271,280
10 percent of the build funded in native USDC on X Layer
Email digest preview
From Aura Brain · Week of Aug 3-9
Your weekly build update
What moved. Development and building permits issued. Site clearing finished; driveway is in.
What is blocked. SIP kit order — flagged 9 days idle against a 12-20 week lead time.
Money position. $30,000 funded to escrow, $10,800 released to the builder, $1,200 held back under the statutory holdback.
Sent weekly and on every material state change. Email delivery is integration-pending; this preview renders the exact template.
Next actions
Place the SIP kit order with the panel plant.
Drawings were approved 9 days ago and the SIP kit is still unordered. Panel lead time is 12-20 weeks from approved drawings, so every idle day pushes lock-up by a day.
You
Overdue
Release the matured holdback on milestone 1 to the builder.
Milestone 1 (Design, engineering & permits) holdback of $1,200 became releasable on 2026-08-04 — the 60-day statutory holdback period has run and it is still held.
You
This week
Get the owner's approval (or a dispute) on milestone 2 so the release can execute.
Milestone 2 (Site prep & foundation) was approved by the builder 7 days ago and is still waiting on the owner's approval before the release can execute.
You
This week
Follow up with the supplier on: final SIP kit quote from the panel plant.
Waiting on the supplier for 14 days: final SIP kit quote from the panel plant. No movement recorded.
Supplier
This week
Fund milestone 03 — SIP shell & envelope
$77,000 to escrow so the shell contract can be signed against funded milestones.
You
Before kit order
Confirm screw-pile install date
Installer holds a tentative week; confirm so site prep and pile crew land together.
Installer
This week
Slip detection runs on the deterministic journey state — the Aura Brain flags stalled steps before they cost weeks (see docs/AI-BRAIN.md).
Budget vs actual
Full budgetSiteDriveway and clearing complete
$8,650 / $8,000
FoundationScrew-pile deposit paid
$4,200 / $10,000
Shell
$0 / $77,000
Interior
$0 / $35,000
Mechanical
$0 / $30,000
Energy
$0 / $48,000
Water
$0 / $17,000
Septic
$0 / $18,000
Extras
$0 / $14,000
Soft costsPermits issued, drawings stamped
$11,420 / $12,000
Contingency
$0 / $32,280
Actuals are committed spend to date against the MID budget column. Categories not yet started show zero — honest numbers, no smoothing.